Maroonthirteen
08-09-2014, 02:19 PM
I entered into a contract in February to build a new home. The contract says I am suppose to take possession in a few weeks. As of today, Floors are not done, no counter tops, or tubs or toilets, a Cabinet isn't square, outside trim needs paint, landscaping not done..... No way he finishes in two weeks.
Anyway, question is, if he isn't finished in time, does that void the contract?
Also, the contract is a standard contract but specifically says I get my earnest money refunded by "builder default". What exactly is builder default? Not finishing on time?
I just want my money back at this point. I'm so fed up with this guy that I would rather find something else.
Thanks
Anyway, question is, if he isn't finished in time, does that void the contract?
Also, the contract is a standard contract but specifically says I get my earnest money refunded by "builder default". What exactly is builder default? Not finishing on time?
I just want my money back at this point. I'm so fed up with this guy that I would rather find something else.
Thanks